BSOP 330 ASH Tutorial / bsop330dotcom

BSOP 330 ASH Tutorial / bsop330dotcom

BSOP 330 Entire Course (Devry)


For more course tutorials visit
www.bsop330.com

BSOP 330 Master Planning All Weeks Discussion Questions Devry University
BSOP330 Week 1 Lab Assignment Problems 4.1, 4.5, 4.9 and 4.11, pages 140-141
BSOP330 Week 2 Lab Assignments Chapter Four Problems 4.23, 4.27, 4.33, and 4.35
BSOP330 Week 2 Southwestern Case study
BSOP330 Week 3 Lab Assignments Chapter 13 problems 13.3, 13.5, 13.9, 13.21
BSOP330 Week 4 Lab Assignments Chapter 12, problems 12.1, 12.5, 12.9, 12.15
BSOP330 Week 4 Quiz
BSOP330 Week 4 Southwestern Case study Printing companies Programs and Inserts
BSOP330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3
BSOP330 Week 5 Quiz
BSOP330 Week 6 Lab Assignments Chapter 14, problems 14.1, 14.3, 14.9, 14.13
BSOP330 Week 7 Case Study Final
BSOP330 Week 7 Lab Assignments Chapter 16, problems 16.1, 16.3, 16.5, and 16.9 (pages 640-641)
BSOP330 Week 7 Quiz




--------------------------------------------------------------------------------------------------------------------------------------------------------



BSOP 330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3 (Devry)

For more course tutorials visit
www.bsop330.com


BSOP330 Master Planning, Week 5, Problem 1
MASTER PRODUCTION SCHEDULE
MAKE-TO-STOCK
Beginning PAB prior to week number one is 500.
If the forecast is larger than the book orders, complete the MPS using the forecast demand. If the booked orders is larger than the forecast complete the MPS using the booked orders
Lead-time for MPS releases is one week.
All MPS releases must be in lot sizes of 250 units.
Period order coverage is one period.
1. Complete the MPS due line and the MPS released line.
2. Complete the PAB line.
3. Complete the ATP line.
BSOP Master Planning, Week 5 Assignment, Problem Two
Make-to-Stock MPS
GIVENS FOR THE MPS PROBLEM:
1. Beginning on-hand inventory prior to week one is 200 units.
2. If the...