Acknowledgement to the Lecturer

Acknowledgement to the Lecturer

ACKNOWLEDGEMENTS

I would like to thank my lecturer Mr. James Hu and tutor Satya Reddy who give all guideline about the assignment and give important hints of the assignment. This work is made by myself based on my personal studies and research and also gives credits to my lecturer who guided me. I would also very pleasure to my tutor Satya Reddy who also guided me in the tutorial task. I also certify that the assignment has not previously been submitted for the assignment in any other course or at any other time in this course.

Table of Content

Acknowledgement

• Task1
a) Pert chart ( Drawn Manually)
b) List the possible of paths and critical path
c) Gantt chart and Network chart (Drawn Manually then screen short )
d) Comparison
• Task 2
Statement of Scope
• Task 3
Event table
• Task 4

Task-1

(a) Draw a PERT chart for the tasks in the table (Manually).

Pert Chart Symbols:

B/3
1). Activity task duration : [B = task, 3 = Duration days]

2). Event :

3). Dummy task :

4). Critical Path :

b) Find and list all possible paths in the PERT Chart, and determine the critical path(s). State the minimum time required to complete the project.

Possible Paths:

1). ABDEFIJO.
2). ACDEFIJO.
3). ABDEFIKO.
4). ACDEFIKO.
5). ABDMNO.
6). ABDGHLO.
7). ACDGHLO.
8). ABDEFLO.
9). ACDEFLO.
10). ACDGHIKO.
11). ACDGHIJO.
12). ABDGHIKO.
13). ABDGHIJO.
14). ACNO.
15). ACHLO.
16). ACHIJO.
17). ACHIKO.
18). ACDMNO.

Critical path:
1). A-B-D-E-F-I-J-O And
2). A-B-D-E-F-I-K-O

The shortest time duration is 31 days in above mentioned project.

c) Using MS Project, enter the above tasks (note: no sub-tasks are required at this stage), then generate a Gantt chart and a Network Diagram

Gantt...