1. (TCO 1) A cost-plus-percentage-fee contract is a: _______. (Points : 5)
cost-reimbursable contract, the seller pays the buyer’s actual costs, and a percentage of the total project costs
cost-reimbursable contract, the seller pays the buyer’s actual costs, and all of the total project costs
cost-reimbursable contract, the buyer pays the seller’s actual costs, and a percentage of the total project costs
cost-reimbursable contract, the seller pays the buyer’s actual costs, and none of the total project costs
2. (TCO 2) The difference between the project manager and contract administrator is: ______.
(Points : 5)
the project manager is responsible for the project-related coordination, while the contract manager is responsible for administering the contract
the contract administrator has the authority to make all contract-related decisions, like approving a change order. The project manager does not have this level of authority.
the project manager is responsible for the administering of the contract, while the contract manager is responsible for project-related coordination.
the project manager has the authority to make all contract-related decisions, like approving a change order. The contract administrator does not have this level of authority.

PROJ 410 FINAL EXAM SET 2
To view more, click on following link:
http://unquite.com/question-details/PROJ-410-FINAL-EXAM-SET-2/760
or email us at:
query@unquite.com

PROJ 410 FINAL EXAM SET 2
1. (TCO 1) A cost-plus-percentage-fee contract is a: _______. (Points : 5)
cost-reimbursable contract, the seller pays the buyer’s actual costs, and a percentage of the total project costs
cost-reimbursable contract, the seller pays the buyer’s actual costs, and all of the total project costs
cost-reimbursable...