PROJ 586 Week 8 Final Exam (Version 1)

PROJ 586 Week 8 Final Exam (Version 1)

PROJ 586 Week 8 Final Exam (Version 1)

Purchase here


http://devrycourse.com/proj-586-week-8-final-exam-version-1



Product Description

• Page 1
1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results, whereas the functional manager is responsible for providing the resources needed to achieve the results.(Points:5)
2. (TCO H) What is the longest phase of the project life cycle? (Points : 5)
3. (TCO B) The lowest level item of any one branch of the WBS is called a(n) _____. (Points : 5)
4. (TCO D) A _____ is a predefined set of actions that will be implemented if the risk event occurs. (Points : 5)
5. (TCO F) ____the project involves measuring actual progress and comparing it to planned progress.(Points : 5)
6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time. (Points : 5)
7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5)
8. (TCO A) Which of the following is not an example of a project? (Points : 5)
9. (TCO C) Why are activities drawn in a serial relationship on a network diagram? (Points : 5)
10. (TCO F) The project cost estimate is allocated to _____. (Points : 5)
11. (TCO F) It is important to use the _____ as the standard against which actual cost is compared. (Points : 5)
12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. (Points : 5)
• Page 2

1. (TCO B) Describe the benefits of including the people who will be involved in performing the project when planning the project. (Points : 10)
2. (TCO E) Part 1: What are some common barriers to team effectiveness? (15 points) Part 2: Describe an example of a team project that would include barriers to...

Similar Essays