QUIZ 1
Question 1
Marks: 1/1
A PMO is NOT used:
Choose one answer.
a. to act as a central repository for project documentation.
b. to replace the project manager as being responsible for the project.
correct
c. as a resource center.
d. as the place where project management improvements are identified and then disseminated to the rest of the organization.
Correct
Question 2
Marks: 0/1
The Larson and Gobeli study that compared projects that had been managed in a variety of structural types revealed that both new product development and construction projects tended to be least effectively executed when the organizational structure was a:
Choose one answer.
a. balanced matrix.
b. functional organization.
c. project organization.
d. project matrix.
incorrect
Incorrect
Question 3
Marks: 0/1
In the Atkinson model of project success, a project's impact to the surrounding community would be classified as:
Choose one answer.
a. a strategic goal.
b. a stakeholder benefit.
c. an element of the iron triangle.
d. an organizational benefit.
incorrect
Incorrect
Question 4
Marks: 1/1
Project members may be from:
Choose one answer.
a. different departments.
b. other organizational units.
c. all of the above.
correct
d. one functional area.
Correct
Question 5
Marks: 0/1
The technical side of project management emphasizes:
Choose one answer.
a. team building.
b. negotiation.
c. budgeting.
d. conflict management.
incorrect
Incorrect
Question 6
Marks: 0/1
Which of the following types of activities is more closely associated with projects rather than processes?
Choose one answer.
a. an activity that is day-to-day
b. an activity that uses existing systems
incorrect
c. an activity that establishes its own work rules
d. an...